Dental Clinic Update:

  • Raised first $6,000 to pay for engineer and to obtain needed permits through the state. (6/2018)  
  • Construction Estimate received from Marquis Builders (8/2018)
  • ​  Estimate received for dental room supplies.​ (8/2018)
  •  1 permit passed through the State. (11/4/18) 
  • Received final permit to start from the State and met with General Contractor (12/6/18).
  • Concrete cut and removed (2/23/19).
  •  Plumbing installed (April/May 2019).
  • ​Electricity installed (June 2019).
  • Framing completed and doors moved (October 2019).
  • Electricity run through framing and overhead lighting set (November 2019).
  • Drywall Complete (January 2021)
  • 1st coat of priming & painting complete (January 2021)
  • Ceiling Grid reworked (January 2021)
  • New lighting & heating/air ducts finished (January 2021)
  • FIRST DAY OF DENTAL SERVICES PROVIDED Sept. 8, 2021

​